Drive south on Broadway toward 23 Road right now and you will hit a single-lane squeeze, orange barrels, and a flagger with a stop sign. Keep going past the intersection and you will find another stretch of road with curb work half finished, a detour sign pointing you toward Vista Grande Road, and a construction fence where Alcove Drive used to connect through. Ask three neighbors what's going on and you will likely get three different answers: a new roundabout, some kind of housing project, road repaving. The projects have different schedules and connections: the roundabout and 23 Road work are tied to Redlands 360, while the CDOT overlay and trail repair are separate projects.
The Roundabout and Related 23 Road Work
The roundabout going in at Broadway (Highway 340) and 23 Road is the piece with an actual finish line attached to it. Site grading began earlier in the spring, with the city's formal construction timeline listing June 1 as the start of the main build. The city and the Colorado Department of Transportation have both said they expect the intersection to be functional by December 2026, weather permitting. Contractor Suncore Construction, which recently built the roundabout at Horizon Drive for the city, is running the job.
The project is not just a new intersection shape. It also includes reconstructing 23 Road from Broadway south to the entrance of the Redlands 360 development, with new curb, gutter, and sidewalk. Access to that stretch of 23 Road is limited to local residents while the work is underway, and South Broadway near the intersection can see temporary closures and shifting traffic patterns. Highway 340 itself stays open to two-way traffic most of the time, but expect intermittent single-lane flagging operations and posted delays through the fall.
A second, unrelated project has added to the confusion. CDOT is overlaying Highway 340 between Redlands Parkway and Grand Avenue, working overnight between 7 p.m. and 7 a.m. on weeknights, and that bridge work is what has closed Alcove Drive at 23 Road, with a signed detour running through Vista Grande Road or Columbine Drive. It shares a corner with the roundabout project but has its own schedule and its own reason for being there. Not every cone in the Redlands traces back to Redlands 360.
The total project cost runs around $5 million. Redlands 360 is covering construction and about 75 percent of that cost, with the city responsible for the remaining 25 percent and for a future second-lane expansion the roundabout is already built to accommodate.
The roundabout wasn't picked out of a design catalog. The city evaluated turn lanes and a signalized intersection first, and only settled on a roundabout after a traffic study conducted as part of the Redlands 360 development review pointed to it as the safer, higher-capacity option for the volumes this corridor is about to see. The city's own engineering and transportation director has described Redlands 360 as one of the largest residential developments Grand Junction has taken on in the past three or four decades. A roundabout built with room to double in capacity is not a response to today's traffic. It's a response to traffic that doesn't exist yet.
The Trail Work That's Already Behind You
Not everything torn up in the Redlands this year is still torn up. Back in late April, the city closed a short stretch of the Redlands Parkway Trail, about three-tenths of a mile near the Blue Heron Boat Ramp where 24 Road becomes Redlands Parkway. That section had been converted from asphalt to concrete in 2023 as part of a broader ten-mile trail upgrade, but riders reported the surface had come out wavy, and the city decided it was worth roughly $100,000 in materials to redo it rather than leave a rough patch on a trail people use every day. Crews detoured cyclists onto the bike lane along Redlands Parkway for about a month, and the section reopened at the end of May.
It's a small fix in the scheme of what's happening at 23 Road, but it's a useful data point. When a stretch of trail wasn't performing the way residents expected, the city redid it inside a single construction season instead of letting the complaint sit. The roundabout and 23 Road work will take considerably longer, but the trail repair is a preview of how these projects tend to resolve here: closed, detoured, fixed, reopened, and then mostly forgotten by the following summer.
Why This Corner Got a Traffic Study in the First Place
Redlands 360 sits on 600 acres south of the Redlands Parkway and Highway 340 intersection, land that was privately owned but open to public hiking and biking for roughly 25 years before development began. The project is planned across a 25-year buildout, with a ceiling of more than 1,300 homes once every phase is complete. That timeline matters more than the total unit count, because it means the traffic pressure on this corridor isn't arriving all at once. It's arriving in stages, and each stage so far has had its own visible construction footprint.
The phases built or underway right now:
- Canyon Rim 360, 22 custom home lots, among the first parcels released.
- Filing One at Easter Hill, 51 single-family homes split between two builders.
- The Corner at Redlands 360, a 125-unit attached townhome development at the southeast corner of South Broadway and South Camp Road, with the first phase of roughly 47 units moving toward vertical construction this fall.
- 4H Peaks, another 47-home phase, with horizontal infrastructure going in this year and homes also planned to go vertical this fall.
- Brothers Boulevard, a new interior road connecting the 23 Road entrance west to Easter Hill, built with its own curb, gutter, sidewalks, and trail alignment as the development's main entry corridor.
Put those together and the roundabout stops looking like an isolated traffic fix. It's the entry point to a road network that's being built out one filing at a time, and the roundabout is built to accommodate future traffic.
The Season at a Glance
| Project | Current status | Expected resolution |
|---|---|---|
| Broadway & 23 Road roundabout | Under construction, single-lane traffic control | December 2026, weather permitting |
| 23 Road reconstruction (Redlands 360 entrance) | Access limited to local residents | Tied to roundabout completion |
| CO 340 overlay, Redlands Parkway to Grand Avenue | Overnight lane closures, Alcove Drive detour to Vista Grande Road or Columbine Drive | Separate CDOT project, its own schedule |
| Redlands Parkway Trail (Blue Heron section) | Reopened | Completed end of May 2026 |
| Corner at Redlands 360 townhomes, phase one | Horizontal work complete, vertical construction starting | Ongoing through fall and winter |
What Fall and Next Spring Probably Look Like
If the roundabout stays on schedule, the single-lane configuration at Broadway and 23 Road should hold through most of the fall and winter before opening in something closer to its final form by the end of the year, assuming weather doesn't push the timeline. The CO 340 overlay and its Alcove Drive detour run on CDOT's own overnight schedule and will clear on their own timeline, separate from whatever happens at 23 Road. In the meantime, expect the townhome phase to bring its own construction traffic through the winter as roughly 47 units go vertical, plus continued grading on 4H Peaks and along Brothers Boulevard as that interior road extends toward Easter Hill.
None of this means the corridor quiets down once December hits. A 25-year buildout with more than 1,300 homes planned means this is closer to the early chapters than the ending. But knowing that the roundabout choice came out of a traffic study conducted during review of the same 600-acre plan, and that the 23 Road work and townhome construction are tied to that plan, means the next round of orange cones won't come as a surprise. You'll be able to look at a filing number or a phase name and know roughly where it fits.
If you've lived in the Redlands long enough to remember when this land was just open hillside for hiking, watching it convert into a mapped, phased neighborhood is its own kind of local history. And if the pace of that change ever has you wondering what it means for your own home, or for a move within the neighborhood down the road, Dee Dee Hansen Simpson has spent more than 30 years tracking exactly this kind of shift across the Grand Valley and is always glad to talk through what it means for you.