The Field House at Colorado Avenue and Rio Grande Avenue, beside Montrose High School, is nearly 40 years old. It gets close to 30,000 visits a year, and its turf field is booked about 75 hours a week. The outdoor pool next to it lasted about as long. Montrose Recreation District says pools like it usually last around 30 years, and the district kept this one going about ten years past that. The pool's final season was summer 2026.
Both changes come from the same decision. MRD is leaving that corner completely. It sold the old building to the school district and bought a bigger one on the Uncompahgre River in Colorado Outdoors. The outdoor pool was not part of the move. Between the two buildings comes a stretch of 2027 with no Field House at all.
One Sale Moved Three Public Uses
The Montrose Recreation District's project page lays out the swap. Montrose County School District is buying the existing Field House, and the sale closed February 24, 2026. MRD is moving its Field House programs to 1227 and 1233 Mayfly Drive, on the Urban Renewal campus inside Colorado Outdoors.
When the deal was announced, the school district's plan for the old building depended on a state grant. That question has since been answered. WesternSlopeNow reported in May 2026 that the district received nearly $6.2 million in BEST funding. With a district match of about $6.4 million, the estimated total is $12.6 million for renovating the 25 Colorado Avenue property into an early childhood center.
Here is where each piece ends up:
| Site | Use through 2026 | What comes next |
|---|---|---|
| Field House, Colorado Ave & Rio Grande Ave | MRD turf, batting cages, Flex Rec, youth and adult leagues | School district early childhood center |
| Outdoor pool beside it | Summer swimming for 40 years | Closed after 2026, with no direct replacement planned |
| Former Secret Creek building, 1227 Mayfly Drive | Colorado Yurt Company operations | New Montrose Field House, opening September 2027 |
The money comes from the same swap. MRD paid $7.5 million in cash for the former Secret Creek building, its land, and an adjacent parcel next to the Riverfront Trail. Design and construction are budgeted at $4.5 million. The district says no new taxes are involved. The money comes from years of savings out of existing taxes and user fees, plus the proceeds from the school district's purchase, and MRD is also applying for grants.
Why the Pool Didn't Make the Move
The pool shows the limits of that budget. MRD says keeping it open would have taken major repairs to the deck, structure, slide foundation, pump house, and mechanical systems, and even those repairs would not have guaranteed many more years. A new community outdoor pool is estimated at $15 million to $25 million. That is roughly three to six times the whole Field House renovation budget, and MRD says the money is not available.
So the district has no current plan to replace the outdoor pool directly. Summer swimming now happens at the Community Recreation Center, which has an open-air, zero-entry pool with a grassy patio. The Montrose Business Times reported the same outcome in February. The district pointed to the pool's age and repair costs and said aquatics would continue at the CRC.
For families who already swam at the CRC, summer 2027 will look about the same. Anyone who walked or biked to the pool by the high school will be swimming somewhere else.
The Gap in 2027
The new building opens in fall 2027. Until then, the old one keeps running for one more winter. The schedule on MRD's project page:
- July through December 2026: design. Public input runs August through December.
- Into early 2027: MRD stays in the existing Field House, ideally through the end of the winter programming season.
- Early 2027: renovation starts at Mayfly Drive.
- Between move-out and September 2027: no Field House programming.
- September 2027: the new Montrose Field House opens for expanded fall programming.
MRD gives the move-out date only as "early 2027." The Montrose Business Times put specific months on it in February. Its report says MRD plans to stay in the existing Field House through March 2027, with no Field House programming between April and August.
These are the people and groups who use that turf now. MRD lists MRD soccer and lacrosse, After School Enrichment, private teams such as Montrose Tribe and Avalanche, batting cage practice, birthday party rentals, groups like the Audubon Society that rent the field and classroom, New Horizon 50+ band practice, and Montrose High School girls' soccer and baseball. MRD has not posted where those programs will go during the spring and summer gap. If your family's spring depends on one of them, ask the program directly.
Flex Rec members have one more open question. MRD says Flex Rec will close before the move, and its equipment will become part of a bigger fitness area in the new building. No closing date has been announced. Pricing hasn't been set either. MRD says membership options for the new building are still under discussion.
What the New Building Puts Next to the River
The building on Mayfly Drive is an open-span structure of about 32,000 square feet. MRD says it will have two artificial turf fields, classrooms and community rooms, fitness areas, and office space for frontline staff. Other options are still under evaluation, including courts, multi-use rooms, soft-surface play areas, and shaded, lit outdoor sport courts.
Demand is the reason for the bigger building. MRD says adult indoor soccer participation has grown more than 45% since 2023, and that the current building limits expansion. The district calls the new building a second premier facility alongside the Community Recreation Center. It says the move improves access for residents in north, east, and west Montrose.
The new location is also part of a neighborhood already in use. The Colorado Outdoors campus map shows the 10-foot-wide Connect Trail and Flex Park along the river. Nearby restaurants include Trattoria di Sofia at 1343 Mayfly Drive, Toasty at 1341 Mayfly Drive, and Shelter Distilling at 947 Mayfly Drive with its riverside patio. Montrose Anglers is on the map too. For a parent, that could change what a practice drop-off looks like. A soccer practice on Mayfly Drive leaves time for a walk on the river trail or lunch at Toasty, which the old corner by the high school never offered.
One financial detail matters for the larger development. As a government entity, MRD doesn't pay property taxes. It has agreed to make voluntary payments to the Montrose Urban Renewal Authority anyway: a fixed $38,815 a year through the end of the TIF period in 2042. That repays infrastructure the authority funded for the site under a 2021 agreement with Secret Creek.
The current occupants of the Mayfly building are moving out. MRD says Secret Creek is relocating but has not shared where. Weehawken, which partnered with MRD for eight years, has found a new location for its programs.
December 9 Is the Last Scheduled Chance to Weigh In
The design is still in progress. MRD hired Reynolds Ash + Associates, a Durango architecture firm, and Stryker and Company of Montrose as construction manager and general contractor. A Design Advisory Group of board members, staff, and community representatives guides the work. MRD held two community open houses on site, in August and September. It says the feedback from those sessions had a real effect on how the building is being designed and programmed. The presentation from the September session, with layouts and renderings, is posted on the project page.
The third session is the last on the published schedule.
Community Open House, Session 3 Wednesday, December 9, 6:00 p.m. On site at the new Montrose Field House, 1227 Mayfly Drive
Design is scheduled to wrap up at the end of 2026, so this session comes in the last weeks before plans are final. This is the place to ask about spring league space, a Flex Rec closing date, or membership pricing for the new building. MRD lists Deputy Director and project manager Jeremy Master and Executive Director Justin Mashburn as contacts for anyone who can't attend.
For more than 30 years I've watched Grand Valley and Western Slope families work their routines around changes like this one. A school drop-off, a practice field, or a summer pool can shape a household's week more than people expect. If you want to talk through how Montrose's recreation changes fit into your plans, I'm glad to help. Denese Hansen Simpson is happy to schedule a consultation.