Mesa County scheduled 32½ Road to close between E Road and E½ Road on October 5. The county's notice says the detour will stay in place until summer 2027. Local access stays open, and crews from Mountain Valley Contracting, Inc. work Monday through Friday from 7 a.m. to 5 p.m. The county finished both ends of the corridor first. This middle piece came last because the county didn't control enough of the land to widen it, and until it's done, the rebuilt ends can't work as one connected route.
Two Finished Ends With a Gap Between Them
Mesa County has been rebuilding 32½ Road in sections since 2021. KKCO 11 News reported in February that the whole Clifton Corridor effort comes to roughly $12 million. The pieces were built in a different order than you'd travel them:
| Segment | What was built | Status |
|---|---|---|
| North end, from the Maverick station to the railroad tracks | Two lanes, widened shoulder, curb and gutter, a 5-foot sidewalk on one side and a 10-foot shared-use path on the other | Finished in 2023 |
| South end, around E Road | New roundabout at E Road, widened and rebuilt canal bridge, road extended south of E Road | County announced completion November 21, 2025 |
| Middle, from the Grand Valley Canal to Front Street | Full rebuild and widening, sidewalks, curb ramps, drainage, roundabout at E½ Road, railroad crossing work, stormwater facility | Closed for construction as of October 2026 |
The south-end project, which the county officially called the 32½ Road and Clifton Campus Roadway Improvement Project, also widened D¾ Road, connected 32½ Road toward D⅞ Road, and added a sidewalk linking Rocky Mountain Elementary Park to nearby homes.
So for about a year, Clifton has had a wide, walkable road at each end of this stretch. Between them sits a road the county describes as largely "built without shoulders or sidewalks, even as the surrounding area continued to develop." A shared-use path that ends at the railroad tracks only gets you as far as the tracks.
Why the Middle Came Last
The delay was about land. In February, as the county was finalizing the design for this middle section, Mesa County Engineering Division Director Laura Page told KKCO 11 News that the county first had to reach agreements with property owners along this stretch:
"There's some areas where it was more of what's called prescriptive use, that we were allowed to use it, but you couldn't widen out with sidewalks and curb and gutter. And then there's other areas where we need temporary construction easements in order to construct these improvements."
That explains the order of the work. The county could drive this part of the road but couldn't add width to it, and adding width is the whole point of the project. Daniel Larkin, Mesa County's senior transportation engineer, described the underlying problem to KJCT: "The Clifton area has developed a lot over the years and in some of those older developments there was not a provision of urban infrastructure. So even though you have an urban housing density and a population there that can use that infrastructure, it wasn't there."
The schedule moved quickly from there. KREX reported that the county put the job out to bid on July 5, opened seven contractors' bids on August 11, and awarded the $4.6 million contract to Mountain Valley Contracting as the lowest qualified bidder. KREX called Phase II one of the largest road construction projects currently under way in Mesa County.
The Intersection the Roundabout Replaces
The biggest single change in Phase II is at 32½ Road and E½ Road. The county says that intersection has had "a high number of broadside crashes," and Phase II replaces its two-way stop with a roundabout. To support the change, the county cites research finding that roundabouts reduce overall crashes by 70% and fatal and injury crashes by more than 80%. Once it's built, 32½ Road will have roundabouts at both E Road and E½ Road.
The railroad crossing is the other bottleneck. A Union Pacific Railroad agreement the county announced July 22 sets Union Pacific's estimated work at $331,552, with Mesa County contributing $5,000 to widen the crossing enough for a sidewalk. That small line item is what lets the walkway on the north segment continue south across the tracks. In its project description, the county says pedestrian safety near the crossing will remain a priority throughout construction.
The Pond by the Canal Goes Back to 2008
The project also includes a regional stormwater detention facility of about 2.3 acres, planned near 32½ Road and the Grand Valley Canal. Its location comes from an older plan. According to Mesa County's September 10 announcement, the county conveyed that vacant property to Housing Resources of Western Colorado in 2008, with the understanding that the organization would develop housing there and build a regional detention facility. Neither one happened.
The updated agreement replaces the 2008 terms. Mesa County will build the facility as part of the road project, and Housing Resources will own, operate and maintain it afterward at its own expense. If Housing Resources needs the facility sooner to keep its own schedule, it can build the facility itself with county approval, and the county could reimburse up to $200,000 in eligible, documented costs.
On the rest of the parcel, Housing Resources plans Crawford Commons Apartments. The proposed first phase has 60 affordable housing units, with room set aside for a possible second phase. The organization expects to complete tax credit and debt financing in spring 2027 and start construction after that. The county's release also says the agreement does not approve the housing development, which still needs financing and the required land use approvals. In that same release, Commissioner Bobbie Daniel is quoted from the September 8 hearing: "Our strongest suit is building infrastructure so people can live their best lives."
The road and the parcel are tied together because the planned facility is meant to handle runoff for both the rebuilt road and future development on the property. As of the county's September 10 release, the design was complete but construction had not started. Folding the facility into the road project gives a property plan that sat idle since 2008 a defined path to the drainage it needs.
Getting Around Until Next Summer
These are the details that matter day to day while the middle stretch is closed:
- Closed segment: 32½ Road from E Road to E½ Road. Local access is maintained, so homes and driveways inside the work zone can still be reached.
- Work hours: Monday through Friday, 7 a.m. to 5 p.m.
- Contractor contact: Mountain Valley Contracting, Inc., 970-644-6560 or [email protected].
- Detour route: The street-by-street route is on the map attached to the county's detour notice. Check it there rather than going by word of mouth.
- Bus riders: Grand Valley Transit Route 10 has closed several stops in the area, and GVT has added courtesy stops along E Road.
Bus riders are dealing with more than this one closure. KJCT reported that GVT began temporary route adjustments across the valley on October 12 because construction is making it hard for buses to stay on schedule. GVT transit planner Andrew Gingerich told the station that the agency tries not to cut large parts of routes, "unless in the case of like Route 10, there is no option because there's no way to detour." GVT has not set a date for routes to return to normal and posts the full list of changes in the news section of its website.
If your usual workaround is I-70, CDOT has a resurfacing project between Horizon Drive and Clifton scheduled from August through November 2026. Expect nighttime single-lane closures, a 12-foot width limit, 55-mph speeds and possible 15-minute delays.
The Clifton Community Campus at 3270 D½ Road sits outside the closed segment. It includes the Clifton Community Center, the Clifton Childcare Center, the Early Childhood Education Center and Training Hub, and the Clifton Library Branch. The campus also hosts Meals on Wheels, youth after-school programming, and CMU Tech adult classes. The library's Clifton Book Club meets October 13 from 10 to 11 a.m., with more sessions listed for November 10 and December 8.
When the Pieces Connect
The county's schedules give two dates. The detour is expected to last until summer 2027, and the full project is scheduled for completion at the end of 2027. KJCT reported a slightly later finish, December 2027 or January 2028, depending on winter weather. The most likely reading is that the road reopens to through traffic first, and finishing work continues after that.
When Phase II is done, 32½ Road will have sidewalks and a widened roadway from Front Street through the railroad crossing and both roundabouts to the rebuilt canal bridge. The finished ends from 2023 and 2025 will finally connect into one route.
If you own a home along 32½ Road or near E½ Road and are deciding whether to list during construction or after the road reopens, I'm happy to walk through how a project like this tends to affect showings, buyer questions and timing. Schedule a consultation with Denese Hansen Simpson and we'll go over your property and the county's schedule together.